Dubrovnik Airport undergoing runway reconstruction Dubrovnik Airport undergoing runway reconstruction Mark Thomas

Dubrovnik Airport undergoing runway reconstruction

By  Mar 11, 2018

The runway and aprons of Dubrovnik Airport are currently undergoing a major overhaul with the works on schedule to be completed by the middle of March.

The current works are the second phase of the development project aimed at increasing the capacity of the airport to almost 4 million passengers a year.

The runway and taxiway works that are in progress will expand the western apron, include the construction of two new rapid exit taxiways, a new east apron and the construction of a new commercial aviation apron on the western side.

runway dubrovnik airport

dubrovnik runway airport 2018 32

Partly cloudy

28°C

Dubrovnik

Partly cloudy
Humidity: 52%
Wind: WNW at 22.53 km/h
Thursday
Mostly cloudy
23°C / 27°C
Friday
Thunderstorms
23°C / 26°C
Saturday
Scattered thunderstorms
21°C / 26°C
Sunday
Partly cloudy
20°C / 25°C

The Voice of Dubrovnik

THE VOICE OF DUBROVNIK


Find us on Facebook

Newsletter

Subscribe to our Newsletter